试卷: LEED v4 OM模拟题A卷英文[查看] A school project has mixed-mode ventilation. During the performance period what does the project need to do for EQ Prerequisite Minimum IAQ?
学校项目采用混合通风。在绩效期,为满足EQ先决条件最低室内空气质量,项目需要? A: Alarm the facility management when indoor air flow rates decrease by 10% from a setpoint 当室内空气速率比设定值低10%时提醒设施管理员 B: Implement the indoor air quality procedure defined in ASHRAE 62.1-2010 实施ASHRAE 62.1-2010中定义的室内空气质量程序 C: Measure outdoor airflow to demonstrate sufficient ventilation is being supplied to the building 测量室外气流,以证明为建筑物提供了足够的通风 D: Replace all air filters on each HVAC unit at least quarterly至少每季度更换每个HVAC装置上的空气过滤器 参考答案: C
本题解释: 选择C,本题解释 A.This is not part of the prerequisite. B.This procedure is not allowed to be used for the prerequisite. C.This is part of the performance period. D.This is not part of the prerequisite. |
|