试卷: LEED v4 OM模拟题D卷英文[查看]   A project team is implementing a fixture and fitting replacement and retrofit policy. Which information should be documented by the MEP engineer for new purchases?
 项目团队正在实施卫生洁具替换与改造,对于新买的设备,MEP工程师需要提供哪些信息
    A: Aggregate fixture calculations 累计洁具计算 B: All fixtures meeting the baseline water consumption of EPAct 1992 所有洁具满足EPAct 1992制定的用水基准线标准 C: Product cutsheets and fixture schedules 产品样本和购买洁具的清单 D: Occupancy usage-based calculations 基于使用次数的用水量计算     参考答案: C 
  本题解释: 选择 C,本题解释The credit documentation would include product cutsheets and fixture schedules showing that all fixtures are WaterSense labeled or equivalent. |   
 
  
 |