试卷: LEED v4 OM模拟题C卷英文[查看]   Which non-mandatory steps could a project team take prior to conducting air-quality testing that would improve the test results?(Choose 2)
 在执行空气质量测试前,项目团队可以采用哪项非强制措施来提升测试结果?(选2项)   A: Install finishes and furniture 安装饰面材料和家居 B: Vacuum using a vacuum cleaner with filtration media 使用带过滤媒介的真空吸尘器 C: Clean with low-emitting cleaning products 用低挥发的清洁产品进行清洁 D: Complete punch-list items that would generate VOCs or other contaminants完成可能产生挥发性有机化合物或者其他化合物的事项 E: Test and balance the HVAC system 对暖通空调系统进行测试平衡     参考答案: BC 
  本题解释: 选择BC,本题解释Here are the required steps before a flush-out or air testing:
 Install all finishes and furniture
 Complete punch-list items that would generate VOCs or other contaminants
 Test and balance the HVAC system
  |   
 
  
 |