Which non-mandatory steps could a project team take prior to conducting air-qual

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-12-22 11:37:54 |只看该作者 |倒序浏览
试卷: LEED v4 OM模拟题C卷英文[查看]
Which non-mandatory steps could a project team take prior to conducting air-quality testing that would improve the test results?(Choose 2)
在执行空气质量测试前,项目团队可以采用哪项非强制措施来提升测试结果?(选2项)
A: Install finishes and furniture 安装饰面材料和家居
B: Vacuum using a vacuum cleaner with filtration media 使用带过滤媒介的真空吸尘器
C: Clean with low-emitting cleaning products 用低挥发的清洁产品进行清洁
D: Complete punch-list items that would generate VOCs or other contaminants完成可能产生挥发性有机化合物或者其他化合物的事项
E: Test and balance the HVAC system 对暖通空调系统进行测试平衡

参考答案: BC

本题解释:
选择BC,本题解释Here are the required steps before a flush-out or air testing:
Install all finishes and furniture
Complete punch-list items that would generate VOCs or other contaminants
Test and balance the HVAC system
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 07:32 , Processed in 0.082832 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部