When conducting a survey as part of the calculations for SS Credit 4 Alternative

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2013-9-21 18:23:36 |只看该作者 |倒序浏览
试卷: LEED AP EB模拟题 A卷[查看]
When conducting a survey as part of the calculations for SS Credit 4 Alternative
Commuting Transportation, which dates/times are the best?
A: A survey conducted each Monday throughout a month.
B: A survey conducted on Monday at the start of a workweek
C: A survey conducted each day starting on Monday and ending on Friday
D: A survey conducted during the summer

参考答案: C

本题解释:
Notes:
See Reference Guide, SS Credit 4, Calculations, Option 3, Survey Timing

The survey needs to occur on five consecutive workdays, or on the Friday at the end o f
a workweek. For circumstances where the building has normal work hours on
weekends, the survey can start/end on those days.

Weeks with holidays must be excluded.

Extreme weather periods should be avoided. Note the question asks what the best
times are. While the summer is accept able, it isn\'t the best choice. USGBC
encourages surveys in spring or fall so t hat weather is not as much a factor.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-8 17:35 , Processed in 0.075483 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部