A project team wishes to get a Credit Interpretation Request on a credit and pre

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-9-26 22:52:42 |只看该作者 |倒序浏览
试卷: LEED GA模拟题F[查看]
A project team wishes to get a Credit Interpretation Request on a credit and prerequisite that are unrelated. What needs to happen?


A: Submit one CIR only, for the prerequisite
B: Submit two CIRs - one each for the credit and prerequisite
C: Submit one CIR only, for the credit
D: Submit one CIR covering both the credit and prerequisite

参考答案: B

本题解释:
A Two CIRs would be needed, not just one for the prerequisite.
B Inquiries must request guidance on just one credit or prerequisite (unless there is technical justification to do otherwise) and generally contain one concise question or a set of related questions.

Projects spend money on CIRs for prerequisites for the same reason as for credits - to find out if a particular solution qualifies the project for meeting the requirements. The project may meet the requirements of the prerequisite but sometimes submitting a CIR is the only way to find out.
C Two CIRs would be needed, not just one for the credit.
D Because the credit and prerequisite are unrelated a CIR must be submitted for each.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-6 00:44 , Processed in 0.075213 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部