试卷: LEED GA模拟题F[查看] A project team wishes to get a Credit Interpretation Request on a credit and prerequisite that are unrelated. What needs to happen?
A: Submit one CIR only, for the prerequisite B: Submit two CIRs - one each for the credit and prerequisite C: Submit one CIR only, for the credit D: Submit one CIR covering both the credit and prerequisite 参考答案: B
本题解释: A Two CIRs would be needed, not just one for the prerequisite.
B Inquiries must request guidance on just one credit or prerequisite (unless there is technical justification to do otherwise) and generally contain one concise question or a set of related questions.
Projects spend money on CIRs for prerequisites for the same reason as for credits - to find out if a particular solution qualifies the project for meeting the requirements. The project may meet the requirements of the prerequisite but sometimes submitting a CIR is the only way to find out.
C Two CIRs would be needed, not just one for the credit.
D Because the credit and prerequisite are unrelated a CIR must be submitted for each.
|
|