试卷: LEED v4 ID+C模拟题A卷英文[查看] A project team is working on three retail spaces located on different sites in the same area. Which statements are true regarding the construction waste management plan(s) required for the projects?(Choose 2) A: The plan(s) must identify at least five types of materials to divert from landfills B: The same plan can be used for all three projects. C: The plan(s) must include an overall project waste diversion goal D: The plan(s) can include hazardous material removal in the project\'s total waste diversion 参考答案: AC
本题解释: Notes A: A CWM plan must list at least five waste streams to divert. B:The plan must be customized for each project. C: A CWM plan must include a diversion goal. D: A hazardous material removal and disposal plan is required in a CWM plan; however, this doesn\'t count toward the total waste diverted or as a separate waste stream (1 of 5 required). |
|