What is the benefit of preparing a concept model for compliance with IP Credit I

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-9-27 14:04:11 |只看该作者 |倒序浏览
试卷: LEED v4 ID+C模拟题B卷英文[查看]
What is the benefit of preparing a concept model for compliance with IP Credit Integrative Process?
A: It can be used to verify the prescriptive requirements are met for EA Prerequisite Minimum Energy Performance
B: It can form the basis of the preliminary energy model for a tenant-lelve energy simulation
C: It can be used as the baseline model for a proposed design
D: It can earn a project extra points when following the prescriptive compliance path of EA Credit Optimize Energy Performance

参考答案: B

本题解释:
选择B,本题解释 When doing a tenant-level energy simulation for EA Prerequisite Option 1, teams must engage a qualified energy modeler to create a preliminary model to aid in design decisions. This model will help as long as there is time to alter the design.
The concept model prepared the project team to create the simple box energy analysis that is part of the Integrative Credit and that can be used as the basis of the preliminary model. The preliminary model analyzes building design configurations and heating and cooling load reduction strategies and is used for Option 1.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 23:38 , Processed in 0.073324 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部