Which of the following activities MUST the CxA perform to comply with Energy and Atmosphere credit, Enhanced Commissioning? (Choose 3)
A: Conduct one commissioning design review of the Owner’s Project Requirements (OPR, Basis of Design (BOD), and design document
B: Review contractor submittals applicable to systems being commissioned
C: Develop a systems manual
D: Review building operation within 10 months after substantial completion with O&M staff and occupants
E: Verify that the requirements for training operating personnel and building occupants are completed

参考答案: ABD

本题解释:
Notes:

See the ‘Requirements’ section of EAc 3

Pay very close attention to what is required of a CxA (Commissioning Authority) for EAc 3 vs. EAp 1

The CxA OR OTHER PROJECT TEAM MEMBERS must develop a systems manual. It does not have to be the CxA.

The CxA OR OTHER PROJECT TEAM MEMBERS must verify that the requirements for training operating personnel and building occupants have been completed. It does not have to be the CxA.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-5-7 06:11 , Processed in 0.075445 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部