试卷: LEED AP BD+C模拟题C[查看] Which of the following activities MUST the CxA perform to comply with Energy and Atmosphere credit, Enhanced Commissioning? (Choose 3) A: Conduct one commissioning design review of the Owner’s Project Requirements (OPR, Basis of Design (BOD), and design document B: Review contractor submittals applicable to systems being commissioned C: Develop a systems manual D: Review building operation within 10 months after substantial completion with O&M staff and occupants E: Verify that the requirements for training operating personnel and building occupants are completed 参考答案: ABD
本题解释: Notes:
See the ‘Requirements’ section of EAc 3
Pay very close attention to what is required of a CxA (Commissioning Authority) for EAc 3 vs. EAp 1
The CxA OR OTHER PROJECT TEAM MEMBERS must develop a systems manual. It does not have to be the CxA.
The CxA OR OTHER PROJECT TEAM MEMBERS must verify that the requirements for training operating personnel and building occupants have been completed. It does not have to be the CxA.
|
|