试卷: LEED AP BD+C模拟题B[查看] A CxA has been selected to perform the fundamental commissioning of a new bank
building. Which of the following must the CxA commission for LEED certification?(choose 2) A: Off-site renewable energy systems B: Lighting and daylighting controls C: HVAC D: Building envelope E: Gravity based water pump 参考答案: BC
本题解释: Notes:
Reference: Energy and Atmosphere Prerequisite, Fundamental Commissioning of Building
Energy Systems,
At a minimum the following energy-related systems must be commissioned:
HVAC
Lighting and daylighting controls
Domestic hot water systems
Renewable energy systems (wind, solar)
Remember - it must be onsite, and it must consume energy.
A gravity based water pump does not consume energy and would not need commissioning.
The building envelope is not one of the minimum systems for Fundamental Commissioning. |
|