试卷: LEED AP EB模拟题 B卷[查看] A project building recently had several ener gy-reducing upgrades, including a new chiller
and lighting enhancements. Only three months of energy use data exists since the
upgrades were installed. What is true regarding the number of points the project team can
earn now that the upgrades have been completed? A: The project team can enter the three months of data into Portfolio Manager to increase the ENERGY STAR rating B: The project team could not earn an ENERGY STAR label with only three months of data C: he project team can include the improvements in the building\'s recertification and achieve more points in the future D: The project team can estimate the annual energy savings to earn more points for the current certification 参考答案: C
本题解释: Notes:
See Reference Guide, EA Credit 1, Calc ulations, Recent Energy Improvements
Because only three months of data is available, annualizing the data to earn more points is
not permitted. The energy savings could only be applied to the future recertification. |
|