A project building recently had several ener gy-reducing upgrades, including a n

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2013-9-21 18:26:37 |只看该作者 |倒序浏览
试卷: LEED AP EB模拟题 B卷[查看]
A project building recently had several ener gy-reducing upgrades, including a new chiller
and lighting enhancements. Only three months of energy use data exists since the
upgrades were installed. What is true regarding the number of points the project team can
earn now that the upgrades have been completed?
A: The project team can enter the three months of data into Portfolio Manager to increase the ENERGY STAR rating
B: The project team could not earn an ENERGY STAR label with only three months of data
C: he project team can include the improvements in the building\'s recertification and achieve more points in the future
D: The project team can estimate the annual energy savings to earn more points for the current certification

参考答案: C

本题解释:
Notes:
See Reference Guide, EA Credit 1, Calc ulations, Recent Energy Improvements

Because only three months of data is available, annualizing the data to earn more points is
not permitted. The energy savings could only be applied to the future recertification.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-9 01:06 , Processed in 0.075720 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部