What should be included in a construction waste management plan for the demolition of an existing building?
A: The design of the size of the building
B: Installation of a composting system for occupants
C: The removal of any CFC-based refrigerants
D: Where to dispose of any PCBs

参考答案: D

本题解释:
Notes:

Reference: LEED 2009 for New Construction and Major Renovations Rating System

The size of the building impacts the quantity of construction waste, but this decision is not part of the construction waste management plan.

Composting would occur post-construction when the building has occupants.

CFC removal would be done by a specialist. This would not be part of the waste management plan.

POLYCHLORINATED BI-PHENYLS (PCB\'s) are a common chemical hazard, in spite of the fact that use has been banned since 1979. They were widely used in older electrical equipment as an insulating fluid.

Hazardous material removal is part of the plan. Hazardous materials do not count toward the percent of debris diverted from landfills but they are still included in the waste management plan.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享1 收藏收藏1
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-5-11 03:01 , Processed in 0.118746 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部