试卷: LEED AP BD+C模拟题D[查看] A school project must complete an additional requirement to qualify for IAQ management
during construction. What additional requirement does this project have to do once the
building is enclosed? A: Use MERV 13 filters instead of MERV 8 filters B: Protect installed absorptive materials from moisture damage C: Prohibit smoking inside the building and within 25 feet of building entrances D: Exceed the SMACNA guidelines 参考答案: C
本题解释: Notes:
Reference: Indoor Environmental Quality Credit, Construction Indoor Air Quality
Management Plan-During Construction, Requirements
This question is for schools which require prohibiting smoking During Construction after
the building is enclosed.
School projects must prohibit smoking in the building and prohibit smoking within 25 feet
of the building entrance once the building is enclosed. |
|