试卷: LEED GA模拟题D[查看] A 10 acre multi-building development has five buildings. How is the LEED boundary determined if each building will be a separate LEED project? A: The LEED boundary is at the perimeter of the ten-acre area B: Each building has the boundary at the edge of a two-acre area C: The project team determines the LEED boundary for each LEED project D: The LEED boundary is at the edge of each building’s footprint 参考答案: C
本题解释: A:The boundary would not be the entire 10 acres for each building.
B:A 10 acre project with 5 buildings does not mean the project will be divided evenly into 5 equally sized 2 acre project areas.
C:The LEED boundary is the portion of the project site submitted for LEED certification. For single-building developments, this is the entire project scope and is generally limited to the site boundary. For multiple building developments, the LEED project boundary may be a portion of the development as determined by the project team. (-USGBC)
D:The boundary would not be set to the edge of the building footprint. |
|