A project team decides to build up instead of out to reduce the building footpri

[复制链接]

203

主题

0

好友

512

积分

超级版主

Rank: 8Rank: 8

跳转到指定楼层
楼主
发表于 2012-9-7 21:49:40 |只看该作者 |倒序浏览
试卷: LEED GA模拟题A[查看]
A project team decides to build up instead of out to reduce the building footprint. This strategy could help earn what credit?
A: Community Connectivity
B: Development Density
C: Heat Island Effect, Roof
D: Maximize Open Space

参考答案: D

本题解释:
Community Connectivity would not be impacted by a change in the building footprint;The density of the project does not change, so this credit would not be impacted; Changing the size of the building footprint (or the roof size) does not help earn a project Heat Island Effect;Reducing the building footprint could result in more open space around the building, assuming it wasn\'t then paved over
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享1 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-5-26 13:34 , Processed in 0.079860 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部