For LEED, if a project has an existing CFC-based refrigeration system and it is

[复制链接]

1759

主题

1

好友

5684

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-9-7 21:49:40 |只看该作者 |倒序浏览
试卷: LEED GA模拟题E[查看]
For LEED, if a project has an existing CFC-based refrigeration system and it is not economically feasible to replace the system, what maximum annual leakage of the existing system is allowed?
A: 3%
B: 0%
C: 1%
D: 5%

参考答案: D

本题解释:
Notes:

Reference: LEED 2009 for New Construction and Major Renovations Rating System
For buildings with existing systems that use CFC-based refrigerants, the systems must be phased out within 5 years after the project is completed, unless a third-party audit shows the simple payback for retrofitting/replacement is more than 10 years.

For such projects, the refrigerant leakage rate must be reduced to no more than 5% each year.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-5-7 05:43 , Processed in 0.077472 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部