A PROJECT is undergoing a major renovation. A whole building energy simulation resulted in
a baseline building performance of $112,488 for the school. Process energy for the school
makes up 25% of the energy costs. What must the design case energy cost be to earn 7
points for Energy and Atmosphere Credit Optimizing Energy Performance?
A: $94,490
B: $96,740
C: $84,366
D: $89,990

参考答案: D

本题解释:
Notes:
Reference: Energy and Atmosphere Credit, Optimize Energy Performance
For existing building renovations to earn 7 points a 20% energy savings must be achieved.
$112,488 X 0.80 = $89,990.
The information about process energy is a distraction. You may be tempted to take $112,488 and
multiply it by 25%, or by 75% to come up with a number.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

0

主题

0

好友

50

积分

版主

Rank: 7Rank: 7Rank: 7

沙发
发表于 2014-6-8 05:21:37 |只看该作者
Major Renovation不是应该用NC么,那就应该是save 24%,$112,488*0.76%才对
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-6-24 02:51 , Processed in 0.101044 second(s), 24 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部