What is an example of a construction hard cost?
A: On-site renewable energy system
B: Payments received from recycled materials
C: Permit fees
D: Measurement and verification of a building’s energy consumption over time

参考答案: A

本题解释:
Notes:

Reference: n/a

Hard costs: By far the largest portion of the expenses in a construction budget, the hard costs are mostly comprised of the actual construction costs incurred to build the project.

Examples include masonry, wood, steel, carpet, tile, mechanical systems, roofing.
A:An onsite renewable energy system is a mechanical system and would be a hard cost.
B:This isn\'t a cost but a potential source of income.
C: Permit fees are a soft cost. A soft construction cost is one that is not directly related to building, construction, etc. These include building permit fees, architect fees, legal, financing, engineering fees, commissioning, and other costs incurred before and after construction.
D:Measurement and verification is a soft cost.

Measurement and Verification plans are used to account for a building\'s energy consumption over time to optimize energy performance, minimize environmental impacts, and save on building operating costs. New Construction projects can earn a Measurement and Verification credit for implementing this type of plan.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享1 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-7 05:25 , Processed in 0.073567 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部