试卷: LEED GA模拟题F[查看] In a state with a closed electricity market, how can off-site green power be purchased? A: Through an ENERGY STAR approved utility provider B: Enroll in a Green-e renewable power program from the utility provider C: Purchase power from a USGBC approved provider D: Have certified wood scraps delivered onsite for burning 参考答案: B
本题解释: Notes:
Reference: Guide to Purchasing Green Power
A:ENERGY STAR does not approve power providers.
B: Some utility companies allow the purchase of renewable energy, sometimes for a price premium. Make sure the source of the energy is Green-e certified for it to qualify for LEED credit.
C:USGBC does not approve power providers.
D:This may help with generating on-site renewable energy. |
|