What impacts a project’s ability to achieve Development Density?
A: Measuring an accurate project boundary
B: Making sure the project has pedestrian access to at least 10 basic services within 1/2 mile
C: Building on a brownfield site in a dense urban area
D: Locating the project near 2 or more bus stops

参考答案: A

本题解释:
The Development Density credit uses the density of the area of the project being built. This density is compared to the densities of other projects within a calculated density radius.

An accurate project boundary is used to determine the project’s density;

Locating the project within 1/2 mile of 10 basic services helps the project earn Community Connectivity;

C item would help a project earn Brownfield Redevelopment;

Locating a project near public transportation can help earn Alternative Transportation, Public Transportation Access.

Reference: LEED 2009 for New Construction and Major Renovations Rating System
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享1 收藏收藏1
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2024-5-26 13:35 , Processed in 0.094673 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部