试卷: LEED AP BD+C模拟题C[查看] A manufacturing building in a southern climate will use extensive photovoltaic panels on the roof to generate electricity. What must occur to
allow the sale of RECs for the on-site renewable energy systems? A: The energy must come from a district energy system B: The project must engage in a 2-year contract with the local utility provider C: RECs equal to 200% of the system’s annual rated energy output each year are purchased from a Green-e eligible source D: The seller must claim the environmental attributes for the on-site system 参考答案: C
本题解释: Notes:
Reference: Energy and Atmosphere Credit, On-Site Renewable Energy, Implementation, Retention of Rene
Renewable Energy Certificates can be sold if two criteria are met.
1. The seller can’t keep the environmental attributes of the energy
2. RECs equal to 200% of the system’s annual rated energy output each year are purchased from a Green-e eligible source |
|