A project has a $10 million materials budget. What estimated value of materials

[复制链接]

262

主题

0

好友

33

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2012-11-15 11:14:03 |只看该作者 |倒序浏览
试卷: LEED AP ID+C 模拟试卷C[查看]
A project has a $10 million materials budget. What estimated value of materials is needed to earn an Innovation in Design point for regional materials?
A: $1.0 million
B: $3.0 million
C: $4.0 million
D: $2.0 million

参考答案: D

本题解释:
This question asks about earning an Innovation in Design point, which includes both exemplary performance and innovative performance, so the requirements are greater than the requirements of the regional materials credit.

For regionally manufactured materials (Option 1) the credit calculation must be 20% or greater.

For regionally extracted, harvested, or recovered as well as manufactured materials (Option 2), the calculation must be 10% or greater.

For exemplary performance the regionally extracted, harvested, or recovered materials as well as manufactured (Option 2), the calculation must be 20% or greater.

$10.0M * 0.20 = $2.0M

Note the differences between Option 1 and Option 2. Option 1 requires manufactured materials only, while Option 2 requires extracted, harvested, or recovered, as well as manufactured materials.

$4M would also earn the point but the question asks for what is needed or the minimum amount required.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-7-7 16:19 , Processed in 0.074348 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部