试卷: LEED v4 GA模拟题A卷[查看] A building owner’s project includes a major HVAC renovation, significant envelope modifications, and core plumbing renovation. An interior fit-out is not part of the project. What LEED rating system would be most appropriate for this project? A: LEED BD+C: Core and Shell B: LEED BD+C: New Construction C: LEED O+M: Existing Buildings D: LEED ID+C: Commercial Interiors 参考答案: A
本题解释: A:LEED BD+C: Core and Shell is appropriate for buildings that are undergoing new construction or major renovation on its exterior shell and core mechanical, electrical, and plumbing units but NOT a complete interior fit-out. (-USGBC)
B:This rating system is appropriate for buildings that are undergoing new construction or major renovation (or gut rehab, for low- and mid-rise residential) and a complete interior fit-out. (-USGBC)
C:This rating system is appropriate for existing whole buildings. Typically, these buildings undergo only improvement work. (-USGBC)
D:This rating system is appropriate for interior spaces that are undergoing alteration work for at least 60% of the certifying gross floor area. (-USGBC)
|
|