试卷: LEED v4 BD+C英文模拟题(A)[查看] A developer has purchased two sites next to each other and plans to combine them in order to develop a new mixed-use project.One of the sites is on the National Priorities List.Which statement is true about the project’s ability to earn LT Credit High-Priority Site? A: The project will not be able to earn the credit. B: The project will earn the credit if the new site area is an infill site. C: The project will qualify for the credit,because a portion of the new site is in the high-priority designated area. D: The project will earn the credit by submitting only the high-priority site for credit documentation. 参考答案: C
本题解释: 正确答案:C
解析:C:If only a portion of the site has a priority designation,it still counts toward the credit. |
|