试卷: LEED v4 BD+C英文模拟题(A)[查看] A project is required to obtain a construction general permit (CGP) prior to construction.Which statement is true about the project achieving SS Prerequisite Construction Activity Pollution Prevention? A: No additional erosion and sedimentation control plan is necessary. B: A project hydrologist must conduct a site evaluation. C: The project team must conduct a site assessment. D: The civil engineer should determine if local code requirements meet or exceed the CGP. 参考答案: A
本题解释: 正确答案:A
解析:A:If the project requires a CGP, the project team has a streamlined path for complying with the prerequisite. No additional ESC plan is needed.
B:This is not necessary because the CGP is required.
C:This is not correct.
D:This is not necessary because the CGP is required. |
|