试卷: LEED v4 BD+C英文模拟题(A)[查看] A project team will not pursue points under WE Credit Indoor Water Use Reduction. Which information should be documented by the MEP engineer for the prescriptive path of WE Prerequisite Indoor Water Use Reduction? A: Aggregate fixture calculations B: Occupancy usage-based calculations C: Product cutsheets and fixture schedules D: All fixtures meeting the baseline water consumption of EPAct 1992 参考答案: C
本题解释: 正确答案:C
解析:C:If a project is using the prescriptive path and not pursuing any credits, documentation would include product cutsheets and fixture schedules showing that all fixtures are WaterSense labeled or equivalent. |
|