试卷: LEED v4 ID+C模拟题A卷英文[查看] Which action does a project team need to take in the discovery phase for water-related systems to earn Integrative Process credit? A: Show how the indoor water demand will be reduced by 30% B: Identify initial responsibilities and deliverables C: Identify at least one on-site, non-potable water source that could supply a portion of at least two demand components D: Document how the water-related analysis informed building and site design decisions in the project\'s OPR and BOD 参考答案: C
本题解释: Notes:C:For IP credit implementation, demonstrate how at least one non-potable water supply source was used to offset at least two water demand components (indoor, outdoor, process).
That\'s key for IP credit: Using non-potable water sources is required for the implementation component. That means for two of the water credits, the project will need to use at least one non-potable water source for reductions. |
|