试卷: LEED v4 ID+C模拟题B卷英文[查看] In an initial goal-setting workshop, which actions would occur? A: Hearing from all community representatives, clarifying functional and programmatic goals, building operations training B: Collection of information about local climates, reviewing EPDs of materials, life cycle analysis of the building design C: Engagement of the owner and primary project team, setting a target certification level, picking LEED credits and assigning re D: Creating a map outlining walking paths to diverse uses, selecting a vendor to purchase RECs from, reviewing power requirement 参考答案: C
本题解释: 选择C,本题解释 Among other things, the initial meeting gets the primary stakeholders together to discuss the project\'s goals, set a target LEED certification level, review potential credits, and assign initial responsibilities to those credits. |
|