试卷: LEED v4 ID+C模拟题C卷英文[查看] A single-story office building has a multiple-zone ventilation system. The ventilation calculations indicate one of the zones does not provide enough air to meet the referenced standard. Which action should the project team take? A: Check if the average airflow of all the zones is enough to meet the requirements B: Increase the size of the air returns in the space C: Install a higher-rated MERV filter to the zone in need of more air D: Increase the supply airflow to the zone in need of more air 参考答案: D
本题解释: Notes:D:All spaces must meet the minimum ventilation requirements. Compare the calculations with the design airflow and revise the design if necessary.
Push more air into the space that doesn\'t meet the minimums and recalculate the ventilation rates. |
|