LEED GAP

 找回密码
 立即注册

QQ登录

只需一步,快速开始

搜索
查看: 287|回复: 0
打印 上一主题 下一主题

A project space is 45,000 SF (4,180 m2) A project team has selected a commission

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-10-2 22:29:59 |只看该作者 |倒序浏览
试卷: LEED v4 ID+C模拟题D卷英文[查看]
A project space is 45,000 SF (4,180 m2) A project team has selected a commissioning agent who is a construction manager not holding any construction contracts. What will the CxA NOT need to do for fundamental commissioning?
A: Coordinate commissioning testing
B: Direct the commissioning team and the process
C: Review results of system performance verification
D: Review building operation within 10 months of substantial completion

参考答案: D

本题解释:
选择D,本题解释The question asks what the agent will NOT need to do for fundamental commissioning.Review the building operation within 10 months of substantial completion is part of enhanced commissioning, not fundamental commissioning.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 16:37 , Processed in 0.087036 second(s), 25 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部