试卷: LEED v4 ID+C模拟题D卷英文[查看] A CxA has arrived on a project site to verify the installation and performance of the systems as part of fundamental commissioning. Which of the following are NOT typical steps the CxA will perform? A: Prefunctional inspections B: Functional performance testing C: Training operating personnel D: Comparing results with the owner\'s project requirements 参考答案: C
本题解释: 选择C,本题解释Not the question uses the word NOT.
When verifying the installation and performance of commissioned systems, three steps are typical.
1. Installation inspections
2. System performance testing
3. Comparison of the results to the original requirements |
|