试卷: LEED v4 OM模拟题B卷英文[查看] A project had one renovation at the beginning of the performance period where 60% of FMR waste was diverted and a second renovation at the end of the performance period where 80% of FMR waste was diverted. What is true about the project\'s ability to earn MR Credit Solid Waste Management - Facility Maintenance and Renovation?
项目在执行期开始时进行了一次翻新,并且转移了60%的FMR废弃物。第二次翻新在执行期的快结束时进行,转移了80%的FMR废弃物。关于项目在MR得分项 固体废弃物管理-设施维护和翻新 说法正确的是? A: 如果项目在整个性能期,转移了至少70%的总FMR废弃物,项目可以获得该分 B: 项目可以获得模范分 C: 项目可以取得该得分 D: 通过绩效期的部分时段推算,项目可以获得该得分 参考答案: A
本题解释: 选择A ,本题解释 A.70% diversion is required for the entire performance period. B.95% diversion of FMR waste earns exemplary performance C.You can\'t average percentages from different renovations and get accurate results. The diverted FMR waste is based on the totals for the performance period, not the relative percentages for each renovation. D.Extrapolation is not allowed |
|