试卷: LEED v4 OM模拟题C卷英文[查看] A 25,000 SF (2,325 m2) mixed-use building is cooled by four rooftop units (RTUs). The building is one storey and includes retail, office, and medical space. How must the cooling system be metered for EA Credit Advanced Energy Metering?
某25000平方英尺的混合用途的建筑,由4组屋顶空调机组提供制冷。这个单层建筑包括零售,办公和医疗空间。为满足EA 得分项 高阶能源计量的要求,制冷系统应如何被计量? A: The RTUs must be metered by occupancy type and operating schedule. 屋顶空调机组必须按照住户类型和运营时间表进行计量 B: The project team can choose how to submeter the RTUs.项目团队可以选择如何对屋顶空调机组进行分项计量 C: The RTUs must be metered separately.这些屋顶空调机组必须被分别计量 D: The RTUs must be metered together.这些屋顶空调机组必须被一起计量 参考答案: B
本题解释: 选择B,本题解释The project team can choose. |
|