试卷: LEED v4 OM模拟题C卷英文[查看] In a mixed-mode system where the mechanical ventilation is inactivated how does the project team confirm that natural ventilation is an appropriate strategy for minimum IAQ?
使用混合模式系统时,当机械通风系统不工作时,项目团队如何确认自然通风系统可以满足最低的室内空气质量? A: 使用英国皇家注册设备工程师协会应用手册AM10 B: 调整或维护每个室外空气进风口,送风机,空气分配系统来满足室外空气进风量 C: 遵循ASHRAE 62.1-2010中室内空气质量程序 D: 完成系统最大室外空气输送率的评估 参考答案: A
本题解释: 选择A,本题解释A.Naturally ventilated projects use the CIBSE AM10 manual to confirm that natural ventilation is an appropriate strategy and if so implement the natural ventilation procedure of ASHRAE 62.1-2010. This is also applicable in mixed mode systems where mechanical ventilation is inactivated. B.This is used for mechanical ventilation. C.For All spaces:The indoor air quality procedure defined in ASHRAE Standard 62.1–2010 may not be used to comply with this prerequisite. D.This is done when systems are unable to meet required outdoor airflow rates. |
|