试卷: LEED v4 OM模拟题D卷英文[查看]   An office project in a cold climate burns natural gas on-site for heating and uses electricity from the grid in warmer seasons for cooling. Which option can be used to mitigate both Scope 1 and Scope 2 emissions?
 某项目用天然气采暖,用电力制冷,哪个选项可以用来抵消Scope 1和Scope 2的排放
    A: RECs or Green Power B: RECs C: Carbon offsets 碳补偿 D: Green Power     参考答案: C 
  本题解释: 选择C,本题解释Scope 1 emissions are direct greenhouse gas emissions from sources owned or controlled by the entity, such as emissions from fossil fuels burned on site. Scope 2 emissions are indirect greenhouse gas emissions associated with the generation of purchased electricity. |   
 
  
 |