试卷: LEED v4 OM模拟题D卷英文[查看] A public utility uses proprietary wireless technology to read the water meter for a project building. Since access to the water-metering data is restricted, which statement is true of the project team\'s ability to achieve WE Prerequisite Building-Level Water Metering?
某项目的水表是远程无线监控的,但是读数是保密的,那么项目团队怎么做可以满足WE先决条件-建筑用水计量的要求? A: The project team can meet the prerequisite by submetering 80% of the potable water use systems. 为80%的自来水消耗安装分项计量 B: The project will achieve the prerequisite because the data is not available. 因为数据无法获取,所以可以直接满足要求 C: The project team can track water usage through monthly billing statements. 可以提交月度水费账单来查阅水耗 D: The project team will need to install a private meter upstream of the public water supply. 需要在用水总管再安装一个水表 参考答案: C
本题解释: 选择C,本题解释A.The potable water use of the whole building and grounds must be metered. C.When the meter is inaccessible, utility bills will suffice. D.A private meter would be installed downstream, not upstream. |
|