试卷: LEED v4 OM模拟题A卷英文[查看]   A project team has completed identifying all equipment that will be included in an energy audit. When coming up with an auditing schedule what should be taken into consideration?(Choose 2)
 项目团队已经确定所有需要包含在能源审计过程中的设备。接下来的审计计划表中需要考虑哪些?(选2项)   A: The location of utility meters 市政仪表位置 B: Acceptable payback period of capital projects 项目可接受的资本回报期 C: The operating schedules of the equipment 设备的运营计划表 D: Length of the performance period 绩效期的长度     参考答案: CD 
  本题解释: 选择CD,本题解释 C.If it\'s summertime you can\'t audit the heating system. D.Because of the seasonal operating times of some equipment the performance period becomes a factor. |   
 
  
 |