A project team in an arid climate is considering using cooling tower blowdown as

[复制链接]

1759

主题

1

好友

5712

积分

管理员

Rank: 9Rank: 9Rank: 9

跳转到指定楼层
楼主
发表于 2016-12-22 11:37:54 |只看该作者 |倒序浏览
试卷: LEED v4 OM模拟题B卷英文[查看]
A project team in an arid climate is considering using cooling tower blowdown as an alternative source of water for irrigation. Which issues should be addressed as a result?(Choose 2)
位于干旱地区的项目团队正在考虑使用冷却塔排污水作为灌溉的替代水源。需要解决哪些问题?(选2项)
A: The timing and reliability of the supply will need to be assessed.需要评估供应的时间和可靠性
B: The water will be unable to be used for turf grass.水不能用在草坪上
C: The evapotranspiration rate of the plants will decrease.植物的蒸腾率将会降低
D: The salinity of the water will need to be tested. 需要测试水的盐度

参考答案: AD

本题解释:
选择AD,本题解释This is a small detail in the reference guide. See WE Credit Outdoor Water Use Reduction/Further Explanation/Alternative Water Sources for more information.
With any alternative water source for irrigation, salinity and storage/availability should be addressed.Irrigating with saline water can cause soil damage.The availability of water for irrigation needs to be enough to last during the peak watering periods.
分享到: QQ空间QQ空间 腾讯微博腾讯微博 腾讯朋友腾讯朋友
分享分享0 收藏收藏0
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

关闭

站长推荐上一条 /1 下一条

Archiver|手机版|LEED GA/LEED AP考试学习平台|版权所有|备案号(沪ICP备11019119号-2)|leedgap   

GMT+8, 2025-9-12 08:39 , Processed in 0.074611 second(s), 26 queries .

Powered by Discuz! X2.5 & Exam 1.4

© 2001-2012 Comsenz Inc.

回顶部